ROAD CLOSURE: A600 – Bedford Road (south of Hurricane Ave) – 14 – 27 September 2026

Location: Bedford Road, A600, south of Hurricane Avenue
  • Traffic management: Road closure
  • Date: 14 Sep – 27 September 2026

Work descriptions

  • Description: S278 – Works for construction of a new table top – with install of new kerbs and footpath to suit. We also need to remove the existing table top which will be planed out and resurfaced at the end – along with all other surfacing works. White-lining to follow.

Applicable Permit Conditions

  • NCT02b: As agreed weekends can be used with the normal HS Section 60 hours. No noisy works to be carried out on Sundays.
  • NCT06a: Pedestrian access to be maintained.
  • NCT07a: Activities shall only take place when relevant road section is closed to traffic.
  • NCT09d: For the activities hereby permitted, it is a condition of this permit that, if there are planned and proposed changes to the traffic management arrangements, the works promoter must notify the authority a minimum of 3 working days before these changes are made.
  • NCT11a: (no details entered)
  • NCT11b: Advance warning signs and Letters to go out a minimum of two weeks before the closure date.

Information for Operational Teams

  • Highway Authority: Central Bedfordshire Council
  • Works reference: UC007S1058
  • Permit reference: UC007S1058-04
  • Permit status: Granted
  • Project reference: UC007H2328
  • Work status: Planned work about to start
  • Footway closure: No
  • TTRO required: Yes